Tower Erection

BTE Energy

While the checking of the approved projects, work schedules and line studies takes place, procurement details about the building site are collected.

Information about access roads, agricultural and forestall areas, required supplies (building materials, concrete, fuel, water, etc.) together with environmental and geographical data, enable us to determine the location of the main building site, adjust schedules and establish priorities.

According to the length of the line and the deadlines, the number of crews and secondary building sites are determined. All line equipment (towers, conductors, OPGW, hardware, etc.) machinery and building materials as well as the personnel are transported to the sites.


Direk Aplikasyonu ve Piketaj:
At the site, BTE Energy’s experienced engineers and topographers ( using the preapproved plan-profile and ROW width diagrams) once more check the alignment of the excavations for the towers and the span between them. Any differences are presented to the owner for approval. At BTE Energy our experienced engineers and topographers pay top notch attention to every detail and variable to ensure flawless erection and installation.

Güzergâhın Açılması ve Ulaşım Yollarının Yapılması:
Grading, logging, access road procurement and building are done in compliance with all necessary regulations and in coordination with government agencies ensuring optimal right of way access.

Direklerin Montaj Faaliyetleri;

Under the personalized supervision of our topographers the holes for the tower footings are excavated. The lean concrete is then poured and leveled ready to set the stubs. Following the previously stipulated tolerances for the foundations, their measurements are checked once more to rule out any possible errors. To ensure the quality and performance of the concrete all necessary equipment is used (poker vibrators, for example) and samples are taken to check the technical specifications and standards. Hammer and core tests may also be performed should the client require so. After pouring the concrete and once the foundations have set according to the specs and standards, the towers are assembled and erected with winches if necessary. The towers are checked ready for the installation of the line.